Information on this page has been provided by the Environment Agency and was correct at the time of upload. The Flood Hub is not responsible for any information held on this page.
Image showing channelisation of the River Mersey through South Manchester. Image: Environment Agency
The River Mersey (flowing through the South Manchester Catchments) contains a significant number of Environment Agency maintained Flood Risk Management assets which are approaching the end of their design life.
Some of the main assets are:
The current management approach involves regular investment in the maintenance of significant lengths of raised earth embankment and revetment which channelise the watercourse, disconnect the river from its floodplain, and which defend only flood plain and recreation / amenity land. This does not align well with current Environment Agency (EA) objectives, targets and aspirations.
The study area was hit heavily by Storm Christoph in January 2021. A major incident was declared and approximately 2,000 properties were evacuated despite the country being in national lockdown due to Covid-19.
A similar event occurred in February 2022 when Storms Eunice and Franklin resulted in the operation of both flood storage basins and record river levels being reached at this location for a second consecutive year. Many Environment Agency assets were damaged in the event resulting in a programme of post flood recovery works amounting to approximately £2.5million.
The current approach to managing flood risk within the study area was endorsed by the 2004 Flood Defence Strategy Plan, which identified a number of phases of works to maintain and / or improve formal flood defences which protect key urban areas in South Manchester; to continue the operation of the two flood storage basins and to maintain a number of key weir structures. In addition, the current Flood Risk Management approach includes maintaining significant lengths of raised embankment and revetment which channelise the watercourse and defend only flood plain and recreation / amenity land.
The first two phases of work identified in the 2004 Flood Defence Strategy Plan were successfully implemented. These initial phases included localised improvements to flood defences in the densely populated areas in East and West Didsbury, Northenden and Heaton Mersey; and remedial works to Northenden and Sale Ees weirs.
However, it is now acknowledged that this previous Strategy Plan is outdated and doesn’t align well with the current EA objectives and targets to achieve Net Zero Carbon by 2030; to maximise potential opportunities for Biodiversity Net Gain and to promote the delivery of WFD mitigation measures.
The current maintenance regime for assets within the study area have now deviated from the 2004 Strategy Plan for several reasons including operational Health and Safety concerns and increasing forecast construction costs. Maintenance activities of key assets are now primarily based on a reactive approach.
In recognition of this, the EA is currently progressing the River Mersey (South Manchester Catchments) strategy project, which has two main objectives:
Objective/Stage 1: Understand the existing Flood Risk Management Assets.
Objective/ Stage 2: Identify a long-term Flood Risk Management approach.
The River Mersey (South Manchester Catchments) Strategy project has two key objectives, which are being delivered in two separate project stages:
The outputs of Stage 1 will be used to develop an Asset Management Plan(s) in accordance with ISO 55000 to effectively manage and operate these assets until a new Flood Risk Management approach has been identified and adopted.
Stage 1 of the project is currently forecast to be completed in winter 2025/26.
Stage 2 of the project will follow on from Stage 1 and its primary output will be the identification of a preferred approach for the future long term (100 years) management of flood risk within the study area.
Programme Timeline summary
Any potential physical works to assets in the study area will not be delivered as part of this Strategy project but will be completed by subsequent projects set up to deliver the recommendations of the Strategy project.
Alongside the Strategy Project there are other flood risk management activities ongoing within the River Mersey (South Manchester Catchments) area. These include works being carried out to repair Northenden Weir, as well as Asset maintenance activities along the embankments of the River Mersey.
More information about the repair works at Northenden Weir can be found by clicking the link below:
Repair Works at Northenden Weir | The Flood Hub
Cheadle Bridge, River Mersey. Image: Environment Agency
The New Years Day floods resulted in erosion of the embankment along several locations. Emergency works are currently underway to protect the banks where there have been breaches, to enable us to operate the basins as they previously operated.
As it stands, the basins would fill from the river and still provide storage and benefit but the rate at which they fill is less controlled. Work has progressed well and the main job of placing large bags to create a protective barrier is almost finished. The Environment Agency will update this further when repairs are complete.
Breached embankment following Ney Years Day Floods in January 2025. Image: Survey Operations on behalf of The Environment Agency