Back to top

Low Crosby Flood Risk Management Scheme

Information on this page has been provided by the Environment Agency and was correct at the time of upload. The Flood Hub is not responsible for any information held on this page.

 

This scheme was completed in October 2022. The constructed solution saw the lowering of an existing 3km long embankment to maximise the natural hydraulic capacity of the floodplain. Even with expected flow increases due to climate change, the 1 in 200-year Standard of Protection (SoP) results in reduced flood risk to 95 residential properties. Zero tonnes of concrete and steel were used in this nature-based solution which reconnects 185Ha of floodplain, restores 3km of river habitat, and has the potential for up to 30,000 tonnes of carbon dioxide to be sequestered over a 100-year assessment period.

Introduction and Background Information

The village of Low Crosby is situated on the right bank of the River Eden approximately 5km north-east of Carlisle in Cumbria. The village is subject to fluvial flood risk from the River Eden which results in the flood water flowing up Willow Beck– a small tributary watercourse to the River Eden which flows through the undefended western part of the village. The village is also subject to flood risk from surface water and artificial drainage systems, with the latter source being heavily influenced by the River Eden flow conditions. The main pre-existing forms of defence for Low Crosby, and the surrounding area, are demonstrated on figure 1 below.

 

Figure 1: Low Crosby and surrounding Eastern existing defences

 

The village has suffered fluvial flooding on multiple occasions historically. In recent years, flooding has occurred because of high flows in the River Eden in January 2005, November 2009, December 2015 (following Storm Desmond) and most recently in February 2020 (following Storm Ciara).

The severe flooding experienced at Low Crosby on 5th and 6th December 2015, as a result of Storm Desmond, was unprecedented. This storm caused a period of prolonged, intense rainfall across Northern England, falling on an already saturated catchment, and led to high river levels and flooding throughout Cumbria and beyond. The flow in the River Eden in to the Carlisle area on 6th of December was the highest ever recorded, resulting in flood levels in some locations of approximately 600mm higher than those experienced during the previous record set in January 2005.

 

Investigations into a potential Flood Risk Management Scheme

In June 2016, the Cumbria Strategic Flood Partnership published the Cumbria Flood Action Plan which set out how flood risk would be managed in an integrated manner at a catchment-wide scale. The plan identifies a need to improve the standard of protection for Low Crosby.

The Environment Agency are the lead organisation currently investigating the viability of improving the standard of protection to Low Crosby as a part of the Low Crosby Flood Risk Management Scheme (FRMS). They are working in partnership with other Risk Management Authorities, such as Cumbria County Council and United Utilities, in order to understand the likely impacts of climate change on flood risk and to determine feasible options to reduce the risk of flooding.

 

The Flood Risk Management Scheme

The Environment Agency Project Team has been working with the stakeholders and the Flood Action Group to identify a preferred option to progress with, in order to reduce the flood risk to Low Crosby. The preferred option identified, involves re-profiling of the existing Warwick Holme flood embankments (see figure 1), to enable flood waters to flow from the River Eden across the Holme during periods of flooding.

By allowing this to occur, the water levels at Low Crosby are reduced sufficiently, which reduces the risk of flooding to the village from the undefended western side (Willow Beck side). The supporting modelling information demonstrates that we can achieve a 1 in 200 year Standard of Protection, based on current data. This is a Standard of Protection of a similar magnitude to a Storm Desmond event (see figure 2).

Figure 2: Visualisation fly through of the proposed scheme and the protection it affords.

 

Start Date of the Construction Works

The programme to take the project through from design to construction sees a start date of Summer 2022.

 

Recommended reading

Comprehensive information about the scheme is provided on the ‘Engagement Pack’ link to the left. Newsletters are provided at 8 week intervals, following the release of the Engagement Pack on 10/05/2021. These give regular updates the status of the project and provide other useful project related information.