Back to top

Kendal Flood Risk Management Scheme

The Environment Agency is delivering a proposed Flood Risk Management Scheme to better protect homes and business from flooding in the Kent catchment, and improve the local environment and community amenities. Kendal is the first area to be delivered, followed by Burneside, Staveley, and Ings, and upstream measures including flood storage. In addition, Natural Flood Management measures are being integrated into the plans which aim to slow the flow of water and provide wider environmental benefits across the catchment.

Introduction

COVID-19 and impacts to delivery of flood risk management schemes

Although we are in a difficult time, the Environment Agency are committed to, and are successfully progressing the delivery of the proposed Flood Risk Management Scheme to better protect residential and business properties from flooding in the Kent catchment, and improve the local environment and community amenities. Whilst construction has started in Kendal, some minor delays may be encountered to the overall programme as a consequence of the impacts of COVID-19. Work will continue to develop the scheme design for Burneside, Staveley and Ings, and upstream measures including storage.


 

Overview

Kendal has a long history of flooding which was experienced most recently during Storm Desmond in 2015, when 2,276 properties and businesses were flooded in Kendal, Burneside, Staveley and Ings. Since then, the Environment Agency along with Cumbria County Council, South Lakeland District Council, United Utilities and other professional partners including the local community identified over 60 different options to address the complex flood issues that affect the catchment. Each option was considered for their technical feasibility, economic viability, environmental sustainability and social acceptability. The preferred option was presented in September 2018.

 

The preferred option takes a catchment based approach and includes a combination of linear defences, improved pumping and conveyance, upstream storage, complimentary natural flood management interventions and wider environmental improvements. The expected construction cost of the scheme is approximately £76 million. Once the scheme is complete, 1,480 homes and 1,151 business in Kendal, Burneside, Staveley and Ings will be better protected. For information on Burneside, Staveley and Ings and upstream measures, click here.

 

Taking a catchment based approach the Flood Risk Management Scheme will be delivered through the Kent catchment as follows:

Kendal Flood Risk Management Scheme
  • Focusing on Kendal, a combination of raised linear defences and improved conveyance will protect homes and businesses from Mintsfeet in the northern end of the town to Helsington Mills in the southern end of the town.

 

Burneside, Staveley and Ings Flood Risk Management Scheme
  • The Flood Risk Management Scheme will protect homes and businesses in the communities of Burneside, Staveley and Ings. The scheme will comprise of linear flood defences, flow routing improvements such as raised kerbs and localised land raising as well as improving the flow of water where the River Gowan joins the River Kent.

 

Upstream Storage, Improved Conveyance, and Natural Flood Management (NFM)
  • Two flood storage areas are proposed on the River Kent, located upstream of Kendal in Kentrigg (volume around 1.7million m3) and upstream of Staveley in Kentmere (1.1 million m3). These two storage areas will limit and control the volume of flood water flowing through Kendal during a flood, providing increased resilience to bridges downstream and enabling more efficient drainage of surface water into the river.
  • A 2km long upper catchment drain from Stock Beck East and North into the River Mint is proposed to reduce the risk of flooding from Stock Beck in the residential area of Sandylands in Kendal.

Upstream storage will provide the necessary storage capacity required to temporarily hold excess flood water during storm conditions. By maximising and formalising the existing floodplain in key upstream locations, it provides the ability to reduce the amount of flood water that flows through the downstream villages and Kendal town. These measures, in conjunction with works to improve conveyance of water and the installation of NFM measures to hold water and slow the flow, provide a suite of effective measures.

These are important elements to complete the scheme, each providing a number of flood risk benefits and playing a vital role in managing excess flows from the upper reaches of the catchment.

For more information on Burneside, Staveley and Ings, and Upstream Measures, click here.

 

Journey Map to Delivery

 


 

Catchment Map

Click the link below to download a map of the catchment that shows the proposed Flood Risk Management Scheme:

 


 

Programme Dates

Construction of the Kendal Flood Risk Management Scheme started in February 2021 and will be complete in 2023. The key programme dates for the scheme are outlined in the table below.

Milestone Start End
Linear Defences at Burneside and Kentrigg Flood Storage Area
Data gathering

Detailed design

Planning submission/approval

Construction

Summer 2020

Summer 2023

Winter 2022

Summer 2024

Spring 2022

Summer 2024

Autumn 2023

2026

Staveley, Ings and Kentmere Flood Storage Area
Data gathering

Detailed design

Planning submission/approval

Construction

Summer 2020

Spring 2023

Spring 2023

Summer 2024

Spring 2022

Summer 2024

Autumn 2023

Autumn 2025

Stock Beck Catchment Drain
Data gathering

Detailed design

Planning submission/approval

Construction

Summer 2020

Spring 2023

Summer 2023

Autumn 2024

Spring 2022

Autumn 2024

Winter 2023

Autumn 2025

Natural Flood Management Projects
Peatland restoration (NFM)

Staveley (NFM)

TBC

April 2020

TBC

March 2021

 

(Dates last updated July 2021)

 


 

Disclaimer

Information on this page has been provided by the Environment Agency and was correct at the time of upload. The Flood Hub is not responsible for any information held on this page. For any enquiries, see the Contact section of the page.

South Lakeland District Council (SLDC) is acting as the accountable body in an Environment Agency (EA) application for European Regional Development Funding (ERDF) to deliver a scheme that is intended to increase the level of flood protection to businesses and residential properties in the North Kendal Industrial Area.

The North Kendal Industrial Area Flood Risk Management Scheme is part of a wider suite of flood risk management measures in the EA scheme that will increase the level of flood resilience and protection to the whole of Kendal.

SLDC was also the planning authority in relation to the EA’s scheme.

SLDC’s role in this process has therefore been administrative – in that it is acting as the accountable body for the funding application – and statutory as the planning authority.