Information on this page has been provided by the Environment Agency and was correct at the time of upload. The Flood Hub is not responsible for any information held on this page. For any enquiries, see the Contact section of the page.



Radcliffe and Redvales Flood Risk Management Scheme (FRMS) aims to reduce the flood risk from the River Irwell south of Bury and west of Radcliffe. Through partnership working with Bury Council the scheme aligns with local strategies for the area including the Bury Local Plan and Flood Risk Management Plan.
There is a long history of flooding in the area from the river overtopping its banks. The Boxing Day 2015 event resulted in flood damage to over 700 residential buildings, multiple commercial properties and critical infrastructure such as Bury Wastewater Treatment Works (WwTW) and electricity substations.
The area also experienced flooding during the storm Ciara extent on the weekend 9th February 2020. Properties on Warth Road, Warth Road industrial park and a property on Parkside Close flooded. The flood event also damaged the flood defence construction site compound at Close Park. The Environment Agency’s contractors, BAM Nuttall, worked quickly to construct temporary defences at Morris Street which successfully defended a number of properties from flooding.
The Environment Agency would like to provide an update for the Hardy’s Gate Bridge Floodgates project, and the piling works that are due to take place on-site soon.
On the north side of the bridge, the floodgates require concrete piled foundations to be installed in the middle of the road, as well as to each side. This activity can only be completed safely by our contractor, AE Yates, under a full road closure, due to the space required around the piling rig.
After discussion with Bury Council, AE Yates have taken measures to schedule this outside of usual daytime working hours. The piling is planned to be carried out during night-time closures.
Please note that the dates / times for which Dumers Lane at Hardy’s Gate Bridge will be under a full road closure will be as follows:
From Monday 7th December to Friday 11th December – each day, full road closure in the evening / night-time, from 8pm to 1am
Normal single lane closure & 4-way control will continue during daytime working hours.
AE Yates and the EA apologise for this inconvenience – a diversion route via Bury Road at Warth Bridge will be in-place at these times.
The piles are installed using an auger (not impact driven). There may be some localised disturbance by noise and lighting during these times. AE Yates are doing the piling works at these times in order to mitigate the disruption of a full closure during daytime working hours.
Thank you for your continued patience and cooperation.
Since Monday 9th November, AE Yates have completed vacuum excavation for a pile platform in the North-Eastern corner. Here they have also removed the road to be replaced in the carriageway, backfilling the redundant gully with concrete.
In the South-Eastern corner, AE Yates have cleared vegetation for the outfall which will drain water from the floodgates, post-flood-event. Alongside this, they have also repaired damage to the kerbs following the excavation of previous trial holes.
Additionally, further works have been completed to the sliding gate supporting rail at the southern floodgate. Here, they have set out plinths as well as drilling and fixing the starter bars and reinforcement for the plinths before the concrete pours for each.
As noted in prior updates, AE Yates have taken actions aiming to resolve the ongoing issues with the Traffic Management system. This has involved the removal of the current remotely operated system, replacing it with conventional timed traffic light units which will be manned during daylight hours.
AE Yates are continuing to work with Electricity North West to remove redundant services located through their trial holes in order that the new ground beam for the floodgates will be able to be installed safely.
On Monday 26th October, AE Yates moved the existing traffic management system to the opposite side of the road, allowing for trial holes to be excavated in the southbound downstream carriageway.
By Wednesday 28th October, AE Yates had excavated the trial holes for the southern floodgate, southbound carriageway and footpath. AE Yates also completed the vacuum excavation of the trial holes at the northern floodgate, recording the services found and restoring the trial holes. On the downstream side, AE Yates completed further vacuum excavation to expose services within the footprint of the pile cap and ground beam intended to be installed there.
AE Yates has also prepared brackets for plinths which will support the beam for the sliding southern floodgate. These will be installed in the southern compound area soon.
On Monday 2nd November, AE Yates completed the temporary backfilling of trial holes in the north-east corner, southbound carriageway and footpath. Trial holes in the south-east corner were completed, alongside placing steel plates in the carriageway and mesh under the footpaths for safety. AE Yates also cleared vegetation and rubble from the area behind the north-eastern wall.
On Tuesday 3rd November, AE Yates located an unknown concrete slab in the north-east section, which required further investigation before proceeding.
On Wednesday 4th November, AE Yates completed the removal of the existing concrete slab as well as the demolition of the wall in the north-eastern corner. AE Yates also began excavation in the north-eastern corner, preparing for the installation of concrete pile foundations.
Following the previous update, AE Yates has been working to resolve the issues with the REMOS traffic management system. The units have now been changed and the supplier is providing attendance during daytime hours.
Both the Environment Agency (EA) and AE Yates appreciate the patience and understanding of affected residents.
The Environment Agency would like to provide an update on the Hardy’s Gate Bridge Floodgates project and the traffic management on site.
Unfortunately, AE Yates’ site team have been dealing with several issues since the installation of traffic management at Hardy’s Gate Bridge on 12th October. On each occasion, they have worked urgently with their traffic management supplier to resolve them.
The Environment Agency is sorry that these problems with the traffic management have occurred, and understands the frustration of local residents who have been travelling near and through the site.
Regrettably, the traffic management supplier has not been able to assure the Environment Agency that its remotely operated system will work reliably, given the connectivity issues experienced to date. AE Yates will therefore be replacing the system with conventional timed units at the earliest opportunity, and these will be manned during daytime working hours.
Before the site works started, the Environment Agency worked with partners, including Bury Council, to evaluate which traffic management system would be best. Based on previous best practice, it chose this system with the expectation that it would operate effectively. However, the system has struggled with site-specific signal issues and, on reflection, our contractor AE Yates needs to make the change to a conventional system.
The Environment Agency apologises for any inconvenience this has caused. AE Yates’ site team are working hard to make the necessary changes as soon as possible to ensure the traffic management arrangements operate effectively going forward.
The Environment Agency would like to provide an update on its Hardy’s Gate Bridge Floodgates project. The Environment Agency’s contractors AE Yates have completed the installation of the 4-way traffic management control on Wednesday 14th October (see figure 1).
On Thursday 15th October, AE Yates completed the dismantling and removal of a stone wall at the upstream corner of the southern floodgate and cleared the area down to a preexisting concrete slab, allowing space for the compound which the sliding gate will be stored in. The materials from the removal of this wall are currently stored in bags onsite as the wall will be reinstated at a later date.
As of 19th October, AE Yates have also completed the removal of tree stumps & branches from the downstream corner of the northern floodgate (see figure 2). This removal uncovered a disconnected power supply and large copper earth straps, which Electricity North West will investigate w/c 26th October. Here, AE Yates have also introduced edge protection on top of the retaining wall. Alongside this, they have also vacuum excavated down to the proposed pile cap and ground beam level.
On 22nd of October, the vacuum excavation was moved to the upstream half of the sliding southern floodgates. These works exposed underground services in the upstream corner, which will require Electricity North West to attend site in future to confirm which services are live and which are redundant. The carriageway trench from the earlier vacuum excavation here has now been backfilled to the underside of the surfacing level (see figure 3).
The Environment Agency and our contractor, AE Yates, recognise the delays and congestion in the vicinity of Hardy’s Gate Bridge, and thanks residents for their patience and understanding.
The Environment Agency would like to provide an update on its Hardy’s Gate Bridge Floodgates project. The Environment Agency advises that its contractor, AE Yates, is due to implement four-way traffic management control from Monday 12th October onwards. This is necessary to allow the contractor to work safely while constructing the floodgate foundations, which run across the full width of the road, both north and south of the bridge.
Following its public engagement and the recent works undertaken by Electricity North West at the bridge, the Environment Agency recognises that the traffic management required over the course of this project is a key concern for local residents. To provide the most efficient and resilient system for those who regularly travel through this location, the Environment Agency will implement a more advanced type of traffic light control. This system is called ‘REMOS’ (remotely operated signals by SRL Traffic Systems). Traffic flow is monitored live and overseen by a central control room, allowing greater efficiency with the aim of reducing congestion.
The Environment Agency understands that Bury Council has recently used this system successfully elsewhere and specifically recommended it as an improved means of traffic control for this project. Nonetheless, the Environment Agency acknowledges that there will unfortunately still be delays and is grateful for residents’ cooperation while the work is ongoing. AE Yates will continue to actively manage how the REMOS system works in practice to ensure that it is operating effectively.
The Environment Agency thanks residents for their patience as these important works progress.
The Radcliffe and Redvales Flood Risk Management Scheme is now focused on the final phase of works, which involves installing flood gates at Hardy’s Gate Bridge. Before construction can begin, Electricity North West are completing a major upgrade to existing electricity cables, with the final stage of this work expected to take place in September 2026. The Environment Agency’s contractor, AE Yates Ltd, will also carry out trial excavations to confirm the location of underground services. Subject to these activities being completed, construction of the flood gates is planned to start from October 2026 and is expected to take around seven months. Traffic management, including four-way traffic controls around Hardy’s Gate Bridge, Dumers Lane, York Street and Gate Lane, will be required for most of the construction period. The Environment Agency and Bury Council are in the process of developing operational procedures for the future deployment of the gates during severe flood events.
Electricity North West will soon begin replacing their cables on Dumers Lane. Their contractor, Network Plus, will carry out the work in two phases:
These works are essential preparation for the Hardy’s Gate Bridge Floodgates project, and must be completed beforehand.
The Environment Agency plans to start building the new floodgates once Electricity North West has finished. This is now expected to be from late summer 2026 onwards. Construction of the floodgates is expected to take around 7 months.
Traffic management will be in place on Dumers Lane during both sets of works to ensure everything can be carried out safely.
We’re sorry for any disruption this may cause and thank residents for their patience while these important works are completed.
The bridge carries many utility services across the river and some of these will need to be diverted or protected before the Environment Agency (EA) commence their works. The EA have been working closely with Electricity North West (ENW) to understand their requirements due to the fragile nature of their cables and identified two major and several minor diversions that need to occur ahead of commencing the works on the flood gate construction. Running concurrently with this scheme is the major upgrade of the existing electricity cables by ENW running the length of Dumers Lane. The EA are working with ENW to complete further enabling works alongside the construction of their major upgrade to reduce disruption to the community and mitigate construction start date delays for the flood gate construction. The EA are in continued communication with ENW to understand their programme and plan to start the construction of the flood gates following completion of their works.
In the meantime, the EA are working with their partners Bury Council to plan and schedule the works, as well as finalising operational procedures for deploying the gates when they would be required. Preparatory vegetation clearance, mostly on the north side of the bridge, was completed in December and further surveying undertaken by their contractor, necessary in advance of mobilising for construction. The works will require road closures and diversions, and theywill seek to minimise duration and impact of these closures on the local community. A Traffic Management Plan has been drafted and shared with Bury Council, and the EA expect to share details of this in their next newsletter.
Currently they are estimating that the works will be carried out in summer 2026, following the completion of ENW’s work and the construction duration is expected to be approximately 7 months.
A visualisation of the gates and their positions on the bridge is shown in figure 1 in the latest newsletter.
The Environment Agency has supplemented the Radcliffe and Redvales scheme through Natural Flood Management (NFM) in the Irwell, Roch and Croal catchments. This is known to have wider benefits than just flood risk, including environmental enhancement, future-proofing against climate change impacts and being a more sustainable option.
The final area of NFM to complete for the project is planned along Stanney Brook, south-east of Rochdale. The EA’s design comprises living ‘leaky’ dams, clay bunds, scrapes and other earthworks which will work by slowing down flow and increasing flood storage area along the Brook, prior to it joining the Roch. In one area of the works, the brook will be realigned to a natural meandering channel, which also serves to slow flow and will have environmental benefits compared to its existing engineered straight course. In total, at least 7500 m3 of additional flood storage would be provided.
A contractor has been appointed by the EA to deliver the works, and they are due to start in late-February 2026, with completion currently scheduled for August. The works will start with vegetation clearance to prepare access routes, then earthworks will be done later in the spring, when drier weather would be anticipated.
Hardy’s Gate Bridge carries many utility services across the river and some of these will need to be diverted or protected before the Environment Agency (EA) commence the installation of moveable flood gates to both the north and south sides of the bridge.
The EA have been working closely with Electricity North West (ENW) to understand their requirements and have identified two major and several minor diversions that need to occur ahead of commencing the works on the flood gate construction. Running concurrently with this scheme is the major upgrade of the existing electricity cables by ENW running the length of Dumers Lane. The EA are continuing to work with ENW to understand their programme and plan to start the construction of the flood gates following completion of their works.
In the meantime, the EA also continue to work with their partners, Bury Council, to plan and schedule the flood gate construction works, as well as develop operational procedures for deploying the gates when they are required. The works will require road closures and diversions, and they will seek to minimise duration and impact of these closures on the local community. Currently the EA are estimating that the works will be carried out in 2026, following the completion of ENW’s work and the construction duration is anticipated to be 7 months.
The EA has supplemented the Radcliffe and Redvales scheme through Natural Flood Management (NFM) in the Irwell, Roch and Croal catchments. This is known to have wider benefits than just flood risk, including environmental enhancement, future-proofing against climate change impacts and being a more sustainable option.
The final area of NFM to complete for the project is planned along Stanney Brook, south-east of Rochdale. The EA’s design comprises living ‘leaky’ dams, clay bunds, scrapes and other earthworks, which will work by slowing down flow and increasing flood storage area along the Brook, prior to it joining the Roch. In total, at least 7,500 m3 of additional flood storage would be provided.
This part of the project is being priced by the EA’s framework contractors, in order to select a preferred supplier. It is currently intended to deliver the work on-site prior to spring 2026.
The primary source of flood risk is fluvial flooding from the River Irwell with a 10% chance of it occurring in any one year. Surface water run-off, artificial drainage systems, reservoirs and a disused canal are also potential sources of flooding in what is a heavily urbanised part of the Irwell catchment. A partnership has been agreed with United Utilities (UU) to address the surface water and drainage issues in the area.
There are a number of different flooding locations along the Project, from upstream at Lower Hinds to Close Park:
The scheme defences have been designed with a 100 year design life and will provide protection against a flood with a 1% chance of occurring in any one year, taking into account predicted climate change increases. The envisaged scheme will reduce flood risk to 1,087 properties currently at risk delivering Present Value benefits of £323.8M.
The scheme is being delivered in three phases:
Phase 1 and 2 of the scheme were delivered as a joint venture for BMMJV with design being delivered by Mott MacDonald and construction delivered by BAM Nuttall.
Phase 3 is being delivered by A.E.Yates.
During the initial detailed design stage of the Radcliffe and Redvales scheme in 2017, a risk was identified that the works had the potential to increase river flows downstream during the worst-case rainfall events.
The original aim to reduce the potential, increased risk of flooding from the scheme, was to construct a flood storage area at Swan Lodge, in Radcliffe. However, it became clear through design development that constructing Swan Lodge storage area wasn’t a viable option. The EA then began to look into other options which included Natural Flood Management (NFM) in the Irwell, Roch and Croal catchments. This is known to have wider benefits than just flood risk, including environmental enhancement, future proof against climate change impacts and being a more sustainable option.
The result of this investigation found there has been some Natural Flood Management already carried out in the catchments which does alleviate some potential increased flood risk posed by the scheme. Examples of some of the Natural Flood Management works that has been carried out in the catchments include at Smithills Woodland Trust and at Holcombe Moor. This Natural Flood Management work has been carried out both by the EA and third parties.
The EA are completing more Natural Flood Management measures on Stanney Brook in the Roch catchment; these are being delivered as part of phase 3. The construction of these would further mitigate the impacts of heavy rainfall and benefit the local communities. For further information on Natural Flood Management please see below the following link: https://thefloodhub.co.uk/nfm/ .
This phase consisted of two components:
Other aspects of this phase included removal of abandoned pipe bridges crossing the River Irwell in two locations on Dumers Lane.
This phase consisted of six components:
See ‘What’s happening now?’ section and the latest newsletter for more information.
The EA secured approval for a business case recommending a scheme to reduce the risk of flooding to the Radcliffe and Redvales communities in May 2019. The project costs are part funded by Grant in Aid from Government (£24.3M). External contributions have been secured from Government Booster Funding (£7M), Local Levy (£3M) and public contributions (£2M pledged by Bury Council).
The Environment Agency’s Natural Flood Management (NFM) works at Stanney Brook, south-east of Rochdale, are now largely complete. The project has delivered a range of measures including leaky dams, clay bunds, scrapes and a section of channel realignment designed to slow the flow of water and create additional flood storage before water enters the River Roch. The Environment Agency’s contractor, Ground Control Ltd, has completed the works, creating approximately 7,500m³ of additional flood storage within the catchment to help reduce downstream flood risk.

Image: Mersey Forest / Rob Dyer. Realignment of the Stanney Brook channel, designed to ‘slow the flow’

Image: Mersey Forest / Rob Dyer. Bunds, scrapes and ‘leaky dams’ installed along Stanney Brook, to increase storage in the flood-plain
Click here to download the Radcliffe and Redvales Flood Risk Management Scheme newsletter about the Stanney Brook Natural Flood Management (NFM) work.
The Environment Agency have changed the existing Flood Warning Areas which cover the River Irwell at Radcliffe and Redvales. They have amended the three existing Flood Warning Areas to reflect their latest understanding of flood risk in the area as the flood risk management scheme nears completion.
To download the information pack from the Community Drop in, click here
An email address has been set up specifically for the Radcliffe and Redvales Flood Risk Management project that can be used for any queries or comments in regards to this project: [email protected].
If you are outside the flood area and would like to be kept up to date with the Radcliffe and Redvales Flood Risk Management Scheme via email, please email [email protected] to be added to the mailing list. They aim to send regular updates as well as quarterly newsletters, and information on when they are holding community drop-ins.
If you would like more information about flood risk, you can email: [email protected].
Visit Bury Council’s website for flood risk information: www.bury.gov.uk/flooding-advice.
You can also follow the Environment Agency on X: @EnvAgencyNW